Your company has signed a contract to construct a parking garage for a client at his new house. You have been assigned to manage the project. The construction must start on 1st November 2018 and be completed in time before he moves into the new house. Table 1 shows the activities that you have planned and the associated costs to complete the garage.

a) Given the information provided in Table 1, construct a Gantt Chart to show the project schedule together with dependencies and float of the activities in the form of CPM analysis and tabulation showing in detail ES, EF, LS, F and TF of each activity.

b) Show in a table the budgeted daily costs and the budgeted daily cumulative costs for the entire duration of the project.

c) A status report after 10 working weeks into the project shows the following information:

Activity A, 100% complete as scheduled, actual cost = RM1,500

Activity B, 100% complete as scheduled, actual cost = RM3,000

Activity C, 50% complete as scheduled, actual cost = RM1,900

Activity D, 100% complete as scheduled, actual cost = RM6,300

Activity E, 100% complete as scheduled, actual cost = RM4,100

Activity F, 50% complete as scheduled, actual cost = RM1,700

Provide an earned-value analysis to evaluate the progress of the project.

Screenshot from 2018-07-30 18-07-06

d) Conclude whether the project is behind or ahead of schedule and provide justifications based on the earned-value analysis.